The overall progress is going well. Enabling works were executed within 3 weeks and this enabled us to commence with the mobilisation of the groundworker on 21st June to commence excavate foundation strip and pads with the pool tank being excavated the following week. You can view some progress photos below.
Works currently in progress:
▪ Installation internal drainage
▪ Preparation to concrete pool shells
▪ Sub-base new MUGA court
▪ Crane pads
Scheduled starting dates of upcoming activities:
▪ Erect steel frame 31 July 2023
▪ Install precast concrete ring beams 7 August 2023