Work is progressing well the on programme for Warsop Health Hub. The steel work is all now erected giving a clear indication of the size and footprint of the new facility. Within the facility it is now possible to see the swimming pool and where the location of the new changing facilities and sports hall will be along with the roof starting to be installed.

A local primary school attended site on 24th October for a Time Capsule burial event to provide a record for future generations to come!

Brick work is due to start week commencing 24th October with the next huge milestone of the building being watertight by 30th November now in sight. Current works are focusing on the roofing, cladding and drainage and work is proceeding well despite the inclement weather that October often brings. Please see some update images below.

Works completed since last report:
Internal floor slabs
Tiling balance tank

Works currently in progress:
Roofing
Cladding
Curtain walling and louvres
External storm and foul drainage